Middle School

Middle School

  • Client ThemeHt
  • Date 10/20
  • Category
  • Location 5th Street, New York, USA

Project Overview

In October 2020, Section31 undertook a complex site development project encompassing multiple facets of GPS data modeling. 

Site Area and Infrastructure Breakdown

  • Building Pad:  90,400sqft – Multi level slab with subterranean storm shelter; 5’ Horizontal overbuild with 3’ over excavation & 3’ select fill.

  • Paving: 138,600sqft – Concrete & HMAC

  • Ponds: 3.7ac

Project Timeline and Deliverables

October 29th: Client submits takeoff request with PDF documents, CAD & takeoff order form.

November 1st: Takeoff delivered with volume report(PDF & Excel), color cut/fill map & KMZ overlay.

November 29th: Project awarded to client with issued for construction plans, CAD & control points provided. Project start date scheduled for March.

December 3rd: GPS model in progress as shown below.

 

December 4th: Rock excavation map and quantities requested by client.

December 5th: Rock surface map provided to client with quantities = 12,549 cubic yards of rock excavation to achieve subgrade.

December 7th: GPS Model completed and delivered to client

GPS KMZ Trimesh

April 2021: Construction complete and ready for students.

complete