9/3/20: Site services contractor makes contact and requests a GPS model for fracking pond; client provides existing topo CAD, survey control points and preliminary diagram and volume requirement of 800,000 barrel capacity.
9/5/20: Preliminary model complete and submitted to client for approval with quantities.
9/9/20: Final model delivered to client.
9/14/20: Per clients request, close out documents provided showing total water volume totaling 804,456 barrels of water at permanent pool elevation; with a finished site surface area of 11.3 acres.