Project Overview
In October 2020, Section31 undertook a complex site development project encompassing multiple facets of GPS data modeling.
Site Area and Infrastructure Breakdown
Building Pad: 90,400sqft – Multi level slab with subterranean storm shelter; 5’ Horizontal overbuild with 3’ over excavation & 3’ select fill.
Paving: 138,600sqft – Concrete & HMAC
Ponds: 3.7ac
Project Timeline and Deliverables
October 29th: Client submits takeoff request with PDF documents, CAD & takeoff order form.
November 1st: Takeoff delivered with volume report(PDF & Excel), color cut/fill map & KMZ overlay.
November 29th: Project awarded to client with issued for construction plans, CAD & control points provided. Project start date scheduled for March.
December 3rd: GPS model in progress as shown below.
December 4th: Rock excavation map and quantities requested by client.
December 5th: Rock surface map provided to client with quantities = 12,549 cubic yards of rock excavation to achieve subgrade.
December 7th: GPS Model completed and delivered to client
April 2021: Construction complete and ready for students.